Check 02 Load management
Load management via Eponet
If Eponet load management is used in addition to integration and billing, the following must be taken into account. Not all charging stations approved for integration can also be used in Eponet load management. Please check whether your desired model is also suitable for Eponet load management.
Requirements:
We recommend a separate network area for e-mobility products, e.g. a VLAN. All e-mobility products should be located in this area. As energy meters require a fixed IP address, please ensure that there is an area for manual IP addresses – or that an assignment via MAC address is set up.
The following must be included in the VLAN:
- Charging stations
- Eponet EdgeServer for load management (DHCP)
- Energy meters in accordance with Eponet approval (fixed IP address required).
The energy meter must be configured 2 working days before the Eponet commissioning date (converter ratio set and fixed IP address). If the energy meters are not configured 2 working days before the Eponet commissioning date, the appointment will be cancelled and a new one must be made.
If the energy meters are not ready for use on site, the time for the additional work or any return visits will be charged separately according to the time and effort involved.
A schematic diagram is recommended for reliable implementation and subsequent support. This will then also be stored on the Eponet portal.